Decision Maker: Director of Economy Transport & Environment
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
1. That the Director approves the details of
the Abbey Road/Shakespeare Road Pedestrian and Cycle Improvements
Phase 2 as set out in this paper.
2. That the Director gives approval to procure, spend and enter
into necessary contractual arrangements to implement this scheme,
at a total estimated cost of £133k, to be funded from a
developer S106 contributions.
3. That the Director gives approval, in consultation with the Head
of Legal Services, to progress all appropriate orders, legal
agreements, deeds of dedication, notices or statutory procedures
and secure any consents, licences, permissions, rights or easements
necessary to enable the Abbey Road/Shakespeare Road Pedestrian and
Cycle Improvements Phase 2 scheme to be implemented.
Publication date: 19/10/2021
Date of decision: 07/09/2021
Accompanying Documents: